The “SAP Certified Application Associate – SAP S/4HANA Project Systems” certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 

NEW QUESTION 46
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NEW QUESTION 47
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 48
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well.
Now, you increase the quantity of the external activity. How does the system support this scenario?

 
 
 
 

NEW QUESTION 49
To which object can you assign a factory calendar?

 
 
 
 

NEW QUESTION 50
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 51
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 52
What could be a reason to use expert mode in the valuation method for results analysis?

 
 
 
 

NEW QUESTION 53
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

 
 
 
 

NEW QUESTION 54
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 55
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.

 
 
 
 

NEW QUESTION 56
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.

 
 
 
 

NEW QUESTION 57
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 58
Cost and Budget
What function are available for period end-closing in the project System?

 
 
 
 
 

NEW QUESTION 59
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

 
 
 
 

NEW QUESTION 60
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

 
 
 
 
 

NEW QUESTION 61
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

 
 
 
 

NEW QUESTION 62
How can you record external service activities with service master data? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 63
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 64
You have created an internally-processed network activity, and assigned a work center and the work. After saving,
you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

 
 
 
 
 

NEW QUESTION 65
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets.
What actions do you have to take to solve the problem?

 
 
 
 

NEW QUESTION 66
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

 
 
 
 

C-TS412-1909 Dumps Full Questions – Exam Study Guide: https://www.prepawaypdf.com/SAP/C-TS412-1909-practice-exam-dumps.html