April 12, 2025

A Fully Updated 2025 PMI-RMP Exam Dumps – PDF Questions and Testing Engine [Q99-Q114]

Rate this post

A Fully Updated 2025 PMI-RMP Exam Dumps – PDF Questions and Testing Engine

Easy Success PMI PMI-RMP Exam in First Try

PMI-RMP Certification is a globally recognized certification that is designed to validate the knowledge and expertise of professionals in the field of risk management. PMI Risk Management Professional certification is offered by the Project Management Institute (PMI) and is targeted towards professionals who work in areas such as project management, business analysis, and risk management. The PMI-RMP certification exam is a rigorous exam that tests the knowledge and skills of candidates in the areas of risk management, risk identification, risk assessment, risk response, and risk monitoring.

The PMI PMI-RMP exam covers a range of topics related to risk management, such as risk identification, assessment, response planning, and monitoring and control. PMI-RMP exam is designed to test the candidate’s knowledge and understanding of these topics, as well as their ability to apply them in real-life scenarios. PMI-RMP exam also assesses the candidate’s ability to communicate effectively with stakeholders and to work collaboratively with team members to manage risks.

 

NEW QUESTION 99
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?

 
 
 
 

NEW QUESTION 100
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.
What is the current project risk exposure?

 
 
 
 

NEW QUESTION 101
When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.
How does centralizing the risk management function help resolve the problem?

 
 
 
 

NEW QUESTION 102
You are the project manager for your organization. You are preparing for the quantitative risk analysis. Mark, a project team member, wants to know why you need to do quantitative risk analysis when you just completed qualitative risk analysis. Which one of the following statements best defines what quantitative risk analysis is?

 
 
 
 

NEW QUESTION 103
You are the project manager of the NHJ project for your company. This project has a budget at completion of
$1,650,000 and you are 60 percent complete. According to the project plan, however, the project should be 65 percent complete. In this project you have spent $995,000 to reach this point of completion. There is a risk that this project may be late so you have taken some measures to recover the project schedule. Management would like to know, based on current performance, what the estimate at completion for this project will be.
What is the estimate at completion?

 
 
 
 

NEW QUESTION 104
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?

 
 
 
 

NEW QUESTION 105
Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe.
What type of risk response has Adrian used in this example?

 
 
 
 

NEW QUESTION 106
A mega facility development project is evaluating some options to achieve the project schedule and budget.
Each option’s success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?

 
 
 
 

NEW QUESTION 107
You work as a project manager for BlueWell Inc. You are performing the quantitative risk analysis for your project. One of the project risks has a 50 percent probability of happening, and it will cost the project $55,000 if the risk happens. What will be the expected monetary value of this risk event?

 
 
 
 

NEW QUESTION 108
You are the project manager for Genpact Inc. You have established quarterly risk management meetings.
Which of the following is not a component of a risk management meeting?

 
 
 
 

NEW QUESTION 109
You are project manager for ABD project. You, with your team, are working on the following
activities:
Probabilistic analysis of a project.
Probability of achieving cost and time objectives.
Trends in Qualitative Risk Analysis results.
On which of the following processes are you working on?

 
 
 
 

NEW QUESTION 110
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

 
 
 
 

NEW QUESTION 111
Rex is the project manager of the BDF Project. This project will last for two years and has a budget of $2,345,000. Management has instructed Rex that the project must not go over budget as funds are very tight in the organization. During the project planning Rex and the project team discover a positive risk event to save $75,000. Rex wants to make certain that this risk event happens so which risk response method is most appropriate?

 
 
 
 

NEW QUESTION 112
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?

 
 
 
 

NEW QUESTION 113
You are the project manager of the GHG project for your company. You have identified the project risks, completed qualitative and quantitative analysis, and created risk responses. You also need to document how and when risk audits will be performed in the project. Where will you define the frequency of risk audits?

 
 
 
 

NEW QUESTION 114
Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than
$125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric’s relationship with the vendor. What positive risk response has happened in this instance?

 
 
 
 

PMI-RMP Study Material, Preparation Guide and PDF Download: https://www.prepawaypdf.com/PMI/PMI-RMP-practice-exam-dumps.html

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below